@@ -112,15 +112,15 @@ OVN makes releases at the following three-month cadence. All dates are
approximate:
+---------------+---------------------+--------------------------------------+
-| Time (months) | Dates | Stage |
+| Time (months) | Example Dates | Stage |
+---------------+---------------------+--------------------------------------+
-| T | Jan 1, Apr 1, ... | Begin x.y release cycle |
+| T | Dec 1, Mar 1, ... | Begin x.y release cycle |
+---------------+---------------------+--------------------------------------+
-| T + 1 | Feb 1, May 1, ... | "Soft freeze" master for x.y release |
+| T + 2 | Feb 1, May 1, ... | "Soft freeze" master for x.y release |
+---------------+---------------------+--------------------------------------+
-| T + 1.5 | Feb 8, May 8, ... | Fork branch-x.y from master |
+| T + 2.5 | Feb 15, May 15, ... | Fork branch-x.y from master |
+---------------+---------------------+--------------------------------------+
-| T + 1.75 | Feb 22, May 22, ... | Release version x.y.0 |
+| T + 3 | Mar 1, Jun 1, ... | Release version x.y.0 |
+---------------+---------------------+--------------------------------------+
Contact
There were three problems: * It was not made very clear that the dates in the table were examples only. * The time period per release only added up to ~2 months, not 3. * The example dates did not agree with the stated time period for branch creation. This commit should fix all three issues. Signed-off-by: Mark Michelson <mmichels@redhat.com> --- Documentation/internals/release-process.rst | 10 +++++----- 1 file changed, 5 insertions(+), 5 deletions(-)